Renton Footbridge Refurbishment
Millar Callaghan were delighted to have been awarded the contract for the refurbishment of Renton footbridge.
This project had to be carried out with minimum disruption to the public and bridge users. After a detailed survey, fabrication drawings were presented to the client for approval.
All fabrication work was carried out at our Irvine workshop. On completion of fabrication a full trial assembly was carried out, to ensure that both sets of new access stairs could be quickly and efficiently installed on site.
Before going to site the new stairs were painted and an anti-slip surface was applied to the deck and stairs.
On site, both stairs were installed and secured to the existing bridge structure in one day.
Share
Categories
More Projects
Queensferry Crossing Internal Access Platforms
Millar Callaghan were awarded the contract to fabricate over 850 tonne of steel platforms, lift…
Newburgh Footbridge Replacement
When Newburgh Footbridge over the Edinburgh to Perth railway line required repair and refurbishment, the…
Gourock Linkspan
The station and pier at Gourock opened in 1889 for pedestrian access only. It wasn’t…
Anderson Footbridge
Originally built in 1969, Anderson footbridge was designed and constructed as a link to a…